One coastal strip
Factory and Spaceport in the Same Place
Starbase co-locates manufacturing, testing and launch, which is what lets Starship iterate as fast as it does.
Starbase sits at Boca Chica on the southern tip of Texas, incorporated as its own city, Starbase, Texas, in 2025. It holds a manufacturing site, a test site and two launch pads, all within a few kilometres, operating around the clock. Both stages are built here, cryo-proofed and static-fired here, stacked here and — through Flight 14 — launched here. That density is the point: a ship can go from the factory floor to the pad without leaving the site, which is why the program’s whole flight history has run through this one location.
SpaceX has invested more than $3 billion in Starbase and Starship systems, and the site is now the reference design for the Florida and Louisiana buildouts. Observed
Production buildings
Starfactory Makes the Parts; the Bays Stack Them
A continuous pipeline from steel coil to a stacked vehicle, about to roughly quadruple in integration capacity.
| Facility | Scale | Role and status | Rated |
|---|---|---|---|
| Starfactory | Parts & subassembly | Operating. Rings, domes and tile work feed the stacking bays next door | Observed |
| Mega Bay 1 & Mega Bay 2 | Six work stations combined | Operating. Current booster and ship stacking | Observed |
| Gigabay | ~116 m tall · ≥24 stations | Under construction on the former High Bay and STARGATE footprint; began 1 July 2025, cladding under way, targeted December 2026. Needed to stack the Block 4 stretch | Building |
| Sanchez / production yard | Staging & sub-assembly | Supporting production area north of the launch site | Observed |
Where the two Mega Bays together offer six work stations, the Gigabay is planned for at least 24 — roughly a fourfold jump in stacking capacity at Starbase alone, matched by a twin Gigabay in Florida.
The two pads
Pad 2 Flies While Pad 1 Is Rebuilt
One pad active, one being reconstructed for rapid reuse and ship catches.
| Pad | Status | Detail | Rated |
|---|---|---|---|
| Orbital Launch Pad 2 (Pad B) | Active | The only active Starship pad; first used on Flight 12, May 2026. Built with a flame trench and a hardened service bunker off to the side | Observed |
| Orbital Launch Pad 1 (Pad A) | Rebuilding | Being rebuilt from the ground up with a new flame trench, refurbished tower arms and shielding for the ship’s flip-and-burn. Two working Starbase pads are hoped for in early 2027 | Building |
Pad 1 flew every mission through Flight 11, then went down for its rebuild; Pad 2 debuted the Block 3 vehicle. The rebuild adds the shielding a ship catch needs, so Starbase is being set up to catch both stages at both towers. Recovery in full is on the Recovery & Landing page.
Massey's & testing
Nothing Flies Until Massey's Signs Off
The cryogenic proof and ship static-fire site, rebuilt after an explosion.
Massey’s is Starbase’s test site, the primary cryogenic proof area for every ship and booster and the stand where ships static-fire before flight. A new multipurpose rig there can squeeze the payload section and test the orbital refueling mechanism. Massey’s was heavily damaged when Ship 36 exploded during propellant loading in June 2025 — a nitrogen COPV failed below its proof pressure and ruptured the methane tank — and was rebuilt with a new electrical and control bunker to harden it against a repeat. Engines themselves are built and fired at McGregor, not here.
Tank farm & ASU
Oxygen Is Moving On Site; Methane Still Arrives by Truck
The propellant chain is covered in full on its own page; here is the Starbase-specific hardware.
The orbital tank farm stores liquid methane, liquid oxygen, liquid nitrogen for subcooling and deluge water, with subcoolers that chill propellant below its boiling point for density; two new methane tanks were added in 2026 for dual-pad operations. An air separation unit has been under construction beside Highway 4 since July 2025 to make oxygen and nitrogen on site, cutting the 200-plus tanker trucks each launch needs by roughly 75%. Methane still arrives as trucked commercial LNG. The whole propellant system, including the Brownsville Linde plant, is on Propellant Supply.
Contested
Deliberately Not Claimed
The load-bearing uncertainties, tagged with the confidence they actually earn.
Two active Starbase pads is a 2027 hope, not a fact. Pad 1’s rebuild has run alongside the Gigabay and has slipped before. Until it flies, Starbase is a one-pad site.
Starbase is also SpaceX’s most dangerous site. It has reported hundreds of injuries to OSHA over the past decade, and a contractor died in a fall in 2025. The pace that makes iteration fast has a safety record attached.
The Gigabay date gates Block 4, not Block 3. Current flights do not need it; the stretched Block 4 vehicle does. A Gigabay slip is a Block 4 slip.
Record
Provenance and Data Sources
- Confidence
- Observed for operating facilities — Building for the Gigabay and Pad 1 rebuild
- Status date
- Q3 2026
- Facilities
- SpaceX Gigabay announcement (March 2025); NASASpaceFlight pad and Massey’s coverage; FAA 2022 Starbase programmatic assessment
- Test site
- Ship 36 anomaly (June 2025) and Massey’s rebuild reporting
- Weakest link
- Pad 1 rebuild timing and the Gigabay completion date